Please be aware that the dates specified are estimates and are subject to confirmation, circumstances and weather permitting.

Sutton Street – Peel Gibson

Widening of road, brick paved parking bays and landscaping.

BRICK PAVING ISLANDS - By the 1st week in November 2009
FOOTPATH/DRIVEWAYS - By the 4th week in November 2009
LANDSCAPING - By the 4th week in November 2009
REINSTATEMENTS - By the 2nd week in December 2009

Crusader Road

MINOR KERBING - By the 4th week in October 2009
REINSTATEMENTS - By the 4th week in October 2009

Philante/Scenic

SMALL ROUNDABOUT TO BE INSTALLED - By the 1st week in November 2009
BRICK PAVING - By the 1st week in November 2009
FOOTPATH - By the 1st week in November 2009

Leslie Street

ROAD WIDENING - By the 2nd week in November 2009.