Thursday, 30 March 2023

Work has now commenced on the replacement of the roof above the indoor 25m pool at the Mandurah Aquatic & Recreation Centre. 

The works are expected to take around 8 months with an anticipated completion of late 2023. 

April 2023 Update: We are happy to announce the we are now moving into Phase 2 of the works. Please view below phases and what the community can expect in each phase of the construction below. 

Phase 1: Design

What is happening? 

  • Contractors on site 
  • Minor activity in car parking area 
  • Some car parking will be redirected to the large overflow carpark opposite the MARC with access on the corner of Adana and Rigel Street

How will customers be impacted? 

  • During Phase 1, impacts to customers will be minimal

Phase 2: Demolition 

What is happening? 

  • Contractors will set up offices on site in the small overflow car parking area
  • Access to the carpark via the entrance directly off Pinjarra Road may be impacted 
  • The removal of the existing pool roof will commence

How will customers be impacted? 

  • For the safety of customers and staff, some programming and services may be impacted as contractors go through the demolition phase
  • There will be no access to the Wellness Centre (spa and sauna) from May and it is anticipated that this function will not be available until project completion
  • Entry to the MARC car park will be limited at the entry directly off Pinjarra Road
  • Customers may be required to access the car park from the south side of the building 

Phase 3: Construction of new roof structure 

What is happening? 

  • Once demolition is complete, the construction of the new roof over the indoor 25m pool will commence. This is expected to take 6 months to complete. 

How will customers be impacted? 

  • For the safety of customers and staff, some programming and services may be impacted as contractors go through the demolition phase
  • There will be no access to the Wellness Centre (spa and sauna) from May and it is anticipated that this function will not be available until project completion
  • Entry to the MARC car park will be limited at the entry directly off Pinjarra Road
  • Customers may be required to access the car park from the south side of the building

View MARC Pool Roof Project page for more info